Kolkata Municipal Corporation uninterrupted power plan flopsBy Riti, Section Kolkata Municipal Corporation
The much-hyped plan of the Kolkata Municipal Corporation (KMC) to supply uninterrupted power to the pumping stations of the city during monsoons, to pump out stagnant water as early as possible has fallen flat after the KMC failed to start work on time.
Initially, the civic body planned to bring three main pumping stations of the city ~ Dhapa Lock Gate Pumping Station, Palmer Bazaar Pumping Station, and the Ballygunge Drainage Pumping Stations ~ under the project.
Citing reasons for the delay, civic officials said that one problem that arose at the time of laying the new electricity connections, was ensuring that the pumps and other existing electrical connections in the pumping stations remained unaffected, at the time of laying the new cables turned out to be a difficult task for the civic authorities.
"We had to ensure that the functioning of the pumping stations and the pumps do not get affected in any way at the time of laying the new cables. This made the entire process laborious and time consuming," a civic engineer said.
"We completed our part of the work on time. It must be some internal matter of the civic body that has held up the work," the official said. Accordingly, a plan to provide uninterrupted power to the pumping stations was mooted. Discussions were also held with the CESC authorities and it was then decided that the only solution available was to have an alternate electricity line for different pumping stations. Source:The Statesman 26thJune2008.